Superstructure of a shunting yard
July 9, 2024

Modernization of the tram in Gdansk

?????????????

Modernization of a two-track tram line with a length of about 4 km divided into 3 sections.

Client: Gdansk Development Division

Amount: 26.5 million euros

Term: 1 year

Estimated completion date: 2019, May

Description:

  • Set of roads and tramways, with a total length of 7.8 km of track to be replaced, as well as fourteen platforms, seventeen grade crossings, sidewalks, and bike lanes.
  • Reinstatement of the affected services, such as sanitation, gas, and storm water networks and electrical and telephone lines and the renovation of existing urban lighting and traffic lights.
  • The new stops will be equipped with an information system for passengers and connected to the TRISTAR monitoring system (Tri-City Intelligent Agglomeration Transport System), an intelligent traffic management system that already operates in several Polish cities.